Blog
Dry and wet tests in progress
Even during the current situation in our company, we are preparing a wastewater treatment plant launch for a bakery near Dunajská Streda. As usual before putting technology in operation, during complex tests we tested correct electrical connection of all machines and their communication with the control system. We also set parameters of measuring devices (level meters, pH and oxygen probes, flow meters, etc.). For a smoother launch of devices, we invited our delivery partners to start the most important machines.
More articles
A friendly visit of our manager to our partners
Our management team travelled across the ocean to visit our partners in North Dakota before technology delivery and start of assembly. The main aim...
Reconstruction of the WWTP for Volkswagen Bratislava: How the potential of bacteria can be used?
Volkswagen Bratislava needed to expand the capacity of the biological part of WWTP. Read about how we did it.