Dry and wet tests in progress

Even during the current situation in our company, we are preparing a wastewater treatment plant launch for a bakery near Dunajská Streda. As usual before putting technology in operation, during complex tests we tested correct electrical connection of all machines and their communication with the control system. We also set parameters of measuring devices (level meters, pH and oxygen probes, flow meters, etc.). For a smoother launch of devices, we invited our delivery partners to start the most important machines.